Thumb Rule Requirement on Construction Field for Civil Engineering

- Advertisement -
- Advertisement -

 

 

  1. Thumb Rule Requirement  

The thumb rule requirement for various work is listed below:

 

a. Thumb Rule of Construction Material

Thumb rule requirement of standard materials and standard calculation in high-raised building

Steel = 3 to 5 kg/ft2

Cement = 0.5bags/ft2

RMC = 0.05 m3/ft2

Block = 12.5 nos /m2

Electrical cast = Rs 133/ft2

Plumbing cost = Rs 126/ft2

Fire fighting cost = Rs 40/ft2

External development = Rs 94.5/ft2

Civil works-Structure = RS 751.25/ft2

Finishing works = RS 467.50/ft2

 

 


 

 

  2. Thumb Rule of Cement Constant  

200 mm in cm 1:6 = 0.124Bags/m2

200 mm in cm 1:4 = 0.206 bags/m2

150 mm in cm 1:6 = 0.093 bags/m2

150mm in cm 1:4 = 0.144 bags/m2

100 mm in cm 1:4 = 0.103 bags/m2

Ceiling plastering = 0.11 bags/m2

Wall plastering = 0.09 bags/m2

Rough plastering = 0.09 bags/m2

Duct plastering = 0.09 bags/m2

External plastering = 0.175 bags/m2

Lathen plastering = 0.55 bags/m2

Stucco plaster = 0.175 bags/m2

100 mm plaster band = 0.012 bags/rmt

PCC 1: 4: 8 = 3.4 bags/m3

PCC 1:5:10 = 2.52 bags/m3

PCC 1:3:6 = 4.2 bags/m3

PCC 1:2:4 = 6.02 bags/m3

230 mm brick = 0.876 bags/m3

115 mm brickwork = 0.218 bags/m3

VDF 100 mm thick = 0.82 bags/m2

Granolithic flooring = 40 mm 0.35 bags/m2

Granolithic flooring = 20 mm 0.28 bags/m2

Anti-skid = 0.28 bags/m2

Ceramic = 0.28 bags/m2

Vertified tile flooring = 0.28 bags/m2

Vertified tile dado = 0.27 bags/m2

Ceramic dado = 0.27 bags/m2

Marble flooring = 0.3 bags/m2

100 mm ht marble skirting = 0.027 bags/rmt

Marble cladding = 0.27 bags/m2

Terracotta tile flooring = 0.3 bags/m2

Mangalore tile = 0.3 bags/m2

Door frame fixing = 0.17 bags/m2

Waterproofing for sunken slab = 0.23 bags/m2

Waterproofing for walls = 0.23 bags/m2

Waterproofing for balcony/toilets = 0.65 bags/m2

Anti terminate treatment chemical Name is chlorpyrifos 20 %.38. Diluting 5 Litre of chemicals with 95 Litre of water and usage is 7.5 Sqm Per liter {Diluted}.

To Provide 1” Dia hole And Deep 1 Foot

 

 


 

 

  3. Labour Productivity Thumb Rule  

 

Brickwork

1 Mason 1 Men mazdoor 1.25 m2

1 Women Mazdoor

 

Wall Plastering

1 mason

1 Men mazdoor 10 m2

1 Women Mazdoor

 

Ceiling

1 mason

1 Men mazdoor 8 m2

1 Women Mazdoor

 

External Plastering

1 mason

1 Men mazdoor 8 m2

1 Women Mazdoor

 

Blockwork 8”

1 mason

1 Men mazdoor 10 m2

1 Women Mazdoor

 

Blockwork 6”

1 mason

1 Men mazdoor 8 m2

1 Women Mazdoor

 

Blockwork 4”

1 mason

1 Man mazdoor 8 m2

1 Women Mazdoor

 

Carpenter

1 Skilled

1 Unskilled 4 m2

 

Bar bender

1 Skilled

1 UN skilled 200 Kg

 

Tile work

1 Mason

1M Mazdoor 10 m2

 

Paint

Painter-skilled OBD 600 ft2

Emulsion 800 ft2

Putty 600 ft2

Primer 800 ft2

 

External Painting

Ace – Low quality

Apex – Medium Quality

Apex Ultima – High Quality

 

 


 

 

  4. The Miscellaneous Thumb Rules in Construction  

One m2 = 10.763 ft2

One m3 = 35.314 ft3

One Acres = 4046.873

m2 = 43560.17

ft2 = 4840.019 Yards

One Cubic meter = 1000 liter

One Meter = 3.280 Feet

One Mile = 1609.344 meter

One Acre = 100 cent

One ground = 2400

Sft = 5.51 cent

½ ground = 2.75 cent

One Mile = 8 Furlong

One cement bag = 1.25 ft3

One Forma box = 1*1*1.25 feet

 


 

 

For Adding 4 Liters of Water in 1 m3 of Freshly Mixed Concrete

The slump value will be increased by 25 mm.

The compressive strength of concrete will be decreased by 1.5 to 2.0 N/mm2

The shrinkage potential will be increased by 10%.

1/4 bag of cement will be wasted.

 

 


 

 

If the Temperature of Freshly Mixed Concrete Is Increased by 1%, Then

4 liters of water per cu.m will give an equal slump.

The air content will be decreased by 1%.

The compressive strength of concrete will be decreased by 1.0 to 1.5 N/mm2.

 

 


 

 

If the Air Content of Freshly Mixed Concrete Is

If increased by 1% then the compressive strength will be decreased by 5%.

If decreased by 1%, the yield will be decreased by 0.03 cu.m per 1 m3.

If decreased by 1%, then the slump value will be decreased by about 12.5 mm.

If decreased by 1%, then the durability of the concrete will be reduced by 10%.

 

This was for the Thumb Rule Requirement.

 

 


 

 

  5. References  

1. Content Filter & Authenticity Checking Team, Dream Civil International

(Our team checks every content & detail to maintain quality.)

 


 

 

Read Also: Quick Setting Cement

 

 

- Advertisement -
Er. Madhu Krishna Poudel
Er. Madhu Krishna Poudel
He is a founder and lead author of Dream Civil International and his civil engineering research articles has been taken as source by world's top news and educational sites like USA Today, Time, The richest, Wikipedia, etc.