  1. Thumb Rule Requirement  

The thumb rule requirement for various work is listed below:

 

a. Thumb Rule of Construction Material

Thumb rule requirement of standard materials and standard calculation in high-raised building

Steel = 3 to 5 kg/ft2

Cement = 0.5bags/ft2

RMC = 0.05 m3/ft2

Block = 12.5 nos /m2

Electrical cast = Rs 133/ft2

Plumbing cost = Rs 126/ft2

Fire fighting cost = Rs 40/ft2

External development = Rs 94.5/ft2

Civil works-Structure = RS 751.25/ft2

Finishing works = RS 467.50/ft2

 

 


 

 

  2. Thumb Rule of Cement Constant  

200 mm in cm 1:6 = 0.124Bags/m2

200 mm in cm 1:4 = 0.206 bags/m2

150 mm in cm 1:6 = 0.093 bags/m2

150mm in cm 1:4 = 0.144 bags/m2

100 mm in cm 1:4 = 0.103 bags/m2

Ceiling plastering = 0.11 bags/m2

Wall plastering = 0.09 bags/m2

Rough plastering = 0.09 bags/m2

Duct plastering = 0.09 bags/m2

External plastering = 0.175 bags/m2

Lathen plastering = 0.55 bags/m2

Stucco plaster = 0.175 bags/m2

100 mm plaster band = 0.012 bags/rmt

PCC 1: 4: 8 = 3.4 bags/m3

PCC 1:5:10 = 2.52 bags/m3

PCC 1:3:6 = 4.2 bags/m3

PCC 1:2:4 = 6.02 bags/m3

230 mm brick = 0.876 bags/m3

115 mm brickwork = 0.218 bags/m3

VDF 100 mm thick = 0.82 bags/m2

Granolithic flooring = 40 mm 0.35 bags/m2

Granolithic flooring = 20 mm 0.28 bags/m2

Anti-skid = 0.28 bags/m2

Ceramic = 0.28 bags/m2

Vertified tile flooring = 0.28 bags/m2

Vertified tile dado = 0.27 bags/m2

Ceramic dado = 0.27 bags/m2

Marble flooring = 0.3 bags/m2

100 mm ht marble skirting = 0.027 bags/rmt

Marble cladding = 0.27 bags/m2

Terracotta tile flooring = 0.3 bags/m2

Mangalore tile = 0.3 bags/m2

Door frame fixing = 0.17 bags/m2

Waterproofing for sunken slab = 0.23 bags/m2

Waterproofing for walls = 0.23 bags/m2

Waterproofing for balcony/toilets = 0.65 bags/m2

Anti terminate treatment chemical Name is chlorpyrifos 20 %.38. Diluting 5 Litre of chemicals with 95 Litre of water and usage is 7.5 Sqm Per liter {Diluted}.

To Provide 1” Dia hole And Deep 1 Foot

 

 


 

 

  3. Labour Productivity Thumb Rule  

 

Brickwork

1 Mason 1 Men mazdoor 1.25 m2

1 Women Mazdoor

 

Wall Plastering

1 mason

1 Men mazdoor 10 m2

1 Women Mazdoor

 

Ceiling

1 mason

1 Men mazdoor 8 m2

1 Women Mazdoor

 

External Plastering

1 mason

1 Men mazdoor 8 m2

1 Women Mazdoor

 

Blockwork 8”

1 mason

1 Men mazdoor 10 m2

1 Women Mazdoor

 

Blockwork 6”

1 mason

1 Men mazdoor 8 m2

1 Women Mazdoor

 

Blockwork 4”

1 mason

1 Man mazdoor 8 m2

1 Women Mazdoor

 

Carpenter

1 Skilled

1 Unskilled 4 m2

 

Bar bender

1 Skilled

1 UN skilled 200 Kg

 

Tile work

1 Mason

1M Mazdoor 10 m2

 

Paint

Painter-skilled OBD 600 ft2

Emulsion 800 ft2

Putty 600 ft2

Primer 800 ft2

 

External Painting

Ace – Low quality

Apex – Medium Quality

Apex Ultima – High Quality

 

 


 

 

  4. The Miscellaneous Thumb Rules in Construction  

One m2 = 10.763 ft2

One m3 = 35.314 ft3

One Acres = 4046.873

m2 = 43560.17

ft2 = 4840.019 Yards

One Cubic meter = 1000 liter

One Meter = 3.280 Feet

One Mile = 1609.344 meter

One Acre = 100 cent

One ground = 2400

Sft = 5.51 cent

½ ground = 2.75 cent

One Mile = 8 Furlong

One cement bag = 1.25 ft3

One Forma box = 1*1*1.25 feet

 


 

 

For Adding 4 Liters of Water in 1 m3 of Freshly Mixed Concrete

The slump value will be increased by 25 mm.

The compressive strength of concrete will be decreased by 1.5 to 2.0 N/mm2

The shrinkage potential will be increased by 10%.

1/4 bag of cement will be wasted.

 

 


 

 

If the Temperature of Freshly Mixed Concrete Is Increased by 1%, Then

4 liters of water per cu.m will give an equal slump.

The air content will be decreased by 1%.

The compressive strength of concrete will be decreased by 1.0 to 1.5 N/mm2.

 

 


 

 

If the Air Content of Freshly Mixed Concrete Is

If increased by 1% then the compressive strength will be decreased by 5%.

If decreased by 1%, the yield will be decreased by 0.03 cu.m per 1 m3.

If decreased by 1%, then the slump value will be decreased by about 12.5 mm.

If decreased by 1%, then the durability of the concrete will be reduced by 10%.

 

This was for the Thumb Rule Requirement.

 

 


 

 

  5. References  

1. Content Filter & Authenticity Checking Team, Dream Civil International

(Our team checks every content & detail to maintain quality.)

 


 

 

Read Also: Quick Setting Cement

 

 

- Advertisement -
Latest Articles

[newsletter_signup_form id=1]

Related Articles
Advertisement